***Sewer Update 06/23/2017***

Work is continuing on the Wickford village sewer project. This is what is planned for next week:

 

  • Sewer construction on the access road between Intrepid Road and Wilson Park will require the access road to be closed from 7 AM to 5 PM weekdays. The access road will be open evenings and weekends.

 

  • The sewer pump station is under construction in the northeast corner of Wilson Park.

 

  • Several sewer forcemain structures will be installed in the center turn lane on Post Road, please drive carefully around the workers.

 

  • This past week, the geotechnical consultant drilled test pits on West Main Street; that work will be complete.

 

  • As noted last week, sewer construction has ended for the summer, to start up again in the village after Labor Day.